AlinemanagerprovidesyouwiththreeestimatesforhisactivityinyourPERTnetwork.Hisestimatesare2weeksoptimistically,4weeksmostlikely,and12weekspessimistically.whichwouldappearonthechart().
A.4 weeks B.5 weeks C.6 weeks D.7 weeks正确答案B
AlinemanagerprovidesyouwiththreeestimatesforhisactivityinyourPERTnetwork.Hisestimatesare2weeksoptimistically,4weeksmostlikely,and12weekspessimistically.whichwouldappearonthechart().
A.4 weeks B.5 weeks C.6 weeks D.7 weeks正确答案B